Facebook

Upcoming Events

12/17/2017 - 03/01/2018
Mural Contest

02/16/2018
MontCo Health Dept. Car Seat Inspection

03/08/2018
Firefighter Cancer Seminar

03/16/2018
MontCo Health Dept. Car Seat Inspection

04/14/2018
Comedy Show

View All Events

2017 Incidents
Jan 47
Feb 52
Mar 43
Apr 41
May 54
Jun 43
Jul 48
Aug 41
Sep 46
Oct 54
Nov 53
Dec 51
Total 573

Past Incidents
2016 555
2015 598
2014 544
2013 449
2012 419
2011 451
2010 449
2009 407
2008 401

Web Counters
Website Visitors
Since
August 16, 2010
1,206,833
Visitors Today
Jan 22, 2018
648

 

Building Progress Updates

Building Progress 11-21-16
 

  • Demolition of the existing building started today and will take approximately two weeks.

                                                                                                                                                                                         

Building Progress 12-5-16

  • Demolition of the existing building completed today.
  • The next few weeks will consist of excavation, surveying and site work for the new building.

                                                                                                                                                                                         

Building Progress 12-28-16

  • Concrete footings for walls and piers began pouring today. This work will continue for approximately two weeks weather permitting.

                                                                                                                                                                                         

Building Progress 1-11-17

  • Concrete continued to be poured for footings and piers. Last pour should be 1-13-17.
  • Masonry contractor started to lay block on exterior walls. This work will continue for approximately two weeks weather permitting.
  • As block walls are built to grade, they will be covered with foam and backfilled.

                                                                                                                                                                                         

Building Progress 1-20-17

  • All exterior block walls have been completed to grade, covered with foam and backfilled.
  • Masonry contractor started to lay block for stair and elevator towers.

                                                                                                                                                                                         

 

Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
Limerick Fire Company
390 W. Ridge Pike
Limerick, PA 19468

Emergency Dial 911
Non-Emergency: 610-489-2222
E-mail: webmaster@limerickfirerescue.org
Copyright © 2018 Firehouse Solutions (A Service of Technology Reflections, Inc.)